2021 Street Improvements - Project #21-1

Construction Update

4/16/21

Moreland Avenue: Delaware Avenue to Charlton Avenue

  • Watermain replacement starting at Delaware and moving east.  
  • The following intersection closures will be necessary to complete the watermain installation:
    • Monday, April 19: Cherokee intersection will be closed 7am-Noon
    • Tuesday, April 20: Smith intersection 7am-2pm
    • Tuesday, April 20: Ottawa intersection 10am-7pm
    • Wednesday, April 21: Galvin intersection 7am-2pm
    • Wednesday, April 21: Ohio intersection 10am-7pm
    • Thursday, April 22: Charlton intersection 7am-7pm
    • Friday, April 23: Seminole intersection 7am-Noon
    • Please understand that this schedule is weather dependent.  

Moreland Avenue: Delaware Avenue to Robert Street

  • Tree removal is currently underway.
  • Private utility contractors (Electric, Gas, Fiber Optics, etc.) will be relocating a few poles.

For everyone's safety, please be alert when driving through the project area!

If you have any questions, please reach out to Ross Beckwith, City Engineer, at rbeckwith@wspmn.gov or 651-552-4130

Get updates directly to your inbox or phone!

Subscribe here to receive timely updates on the 21-1 Project as soon as they come out!

2021 Street Improvement Documents

2021 Moreland Avenue Reconstruct – Notice of Project Starting April 12th, 2021