2017 Street Improvement – Project #17-1

The West St. Paul City Council recently awarded the construction work on this year’s Street Improvements Project to Palda & Sons Construction, Inc. out of St. Paul. 

It is our intention to keep the neighborhood informed on this project as much as possible. To that end, the City will be creating a weekly update that will be posted here by Friday afternoon each week. 

What to expect for week of May 1st


Fox Ridge Court
Pouring concrete curb/aprons will finish up.  Concrete crews will be in pouring driveway aprons. Do not drive over newly poured concrete for 7 days.

Bidwell Street
Saint Paul Regional Water Service will continue water main replacement. Residents will have access to their driveway at the end of each day, except after concrete curb/aprons are poured in which case they can park overnight directly in front of their driveway.

Runge Lane
Roadway grading and possibly the first lift of asphalt Monday morning (May 1st).

Humboldt Ave
Sanitary sewer lining was completed. If residents notice any unusual sewer issues, please contact City Hall immediately.

Kraft Road
Sanitary sewer lining was completed. If residents notice any unusual sewer issues, please contact City Hall immediately.

Edith Drive
Sanitary sewer lining was completed. If residents notice any unusual sewer issues, please contact City Hall immediately.

Charlton Street
Xcel Gas will continue installing new gas mains behind the curb.

Sherwood Court
Xcel Gas will begin installing new gas mains behind the curb.

Edgewood Lane
Xcel Gas will begin installing new gas mains behind the curb.

Contact

Darin Rezac


Civil Engineer
651-552-4131
drezac@wspmn.gov

Ross Beckwith


City Engineer/Parks and Public Works Director
651-552-4130
rbeckwith@wspmn.gov