2017 Street Improvement – Project #17-1

The West St. Paul City Council recently awarded the construction work on this year’s Street Improvements Project to Palda & Sons Construction, Inc. out of St. Paul. 

It is our intention to keep the neighborhood informed on this project as much as possible. To that end, the City will be creating a weekly update that will be posted here by Friday afternoon each week. 

What to expect for week of June 26th


Fox Ridge Court
All scheduled work has already been completed.

Bidwell Street
The contractor has finished installing the curb & gutter as well as the concrete approaches for the driveways. The first layer of bituminous pavement is scheduled to be laid on Wednesday, June 28th.  Work is scheduled to take one full day with residents being able to access their driveways in the afternoon.

Runge Lane
All scheduled work has already been completed.

Humboldt Ave
Preliminary utility work will be beginning.  Representatives from SPRWS will be in the area in preparation for installing temporary water service while the new water main is installed. Trees and shrubbery that are in the City right-of-way and previously marked will be removed.

Kraft Road
Preliminary utility work will be beginning.  Representatives from SPRWS will be in the area in preparation for installing temporary water service while the new water main is installed.

Edith Drive
The contractor will continue grading on Edith Dr. between Charlton Ave. and Bellows St. in preparation for concrete curb & gutter which is scheduled for Wednesday, June 28th. Concrete driveway aprons will be installed following installation of the curb and gutter.  Xcel Gas will continue the process of installing new gas lines on Edith between Smith Ave and Charlton Ave.

Charlton Street
Xcel Gas will continue with gas main work behind the curb.  

Sherwood Court
Xcel Gas will continue with gas main work behind the curb. 

Edgewood Lane
Xcel Gas will continue with gas main work behind the curb.

Contact

Darin Rezac, PE


Civil Engineer
651-552-4131
drezac@wspmn.gov

Ross Beckwith, PE


City Engineer/Parks and Public Works Director
651-552-4130
rbeckwith@wspmn.gov